Gerard Beekmans - 2003/09/10
I propose the following plan.
* Resolve that Bison issue. Tomorrow night deadline: either find a patch that works, or leave it alone and deal with it at a later date.
* Fix all oustanding P1 bugs by the end of the week
* Release LFS-5.0-RC1 Monday, Sep 15th and spend that entire week testing the book.
* If major issues have come up, release LFS-5.0-RC2 on Monday, Sep 22nd and spend that week testing as well.
* If no major issues came up, instead of releasing LFS-5.0-RC2 on the 22nd, we can release LFS-5.0 itself.
Testing and QA teams: is this plan workable taking your own schedules and available time into consideration. This timeline stands and breaks with your availability, so this is of course flexible and can be changed before we commit to anything.
呵呵,看到了吧?
9月15号星期一发布LFS-5.0-RC1,然后用整整一个星期的时间来测试。如果发现问题,就在9月22日发布LFS-5.0-RC2;如果没问题,那么9月22日就发布LFS-5.0了!
http://linuxfromscratch.org/news ... fs50revisedtimeline |
|